Here,
I have compiled most of the question were asked to me. Of course, I am not
going to list here the irrelevant irritating ones that some HR still ask for no
reason.
These
questions are mainly for a Construction planner and Primavera P6 &
MS user. Answers are as per my best knowledge, and
your opinion may differ although I took help from different resources later on
while writing this article.
Interview
Questions for a Planning Engineer
contain versatility of information regarding all
the project management
fields.
The
planning engineer is one of the most critical people in any project. All the
project related information is on his/her fingertips all the time, and you call
it the right hand of any project manager alongside a project engineer.
Let’s see what kind of questions a planning
engineer have to face in an interview.
Question-1:
What is a Base Project Schedule?
Answer: A baseline is an approved
program by both parties which is used as a benchmark to measure the progress of
a project.
Question-2:
What is the Main Driver of a Project and how you will get it?
Answer: The main driver consists of
the significant activities that are driving the project at the critical path. To
get it just go to last activity and check its driving activity, then go to that
driving activity and mark its driving also, same goes until you reach the first
activity. This is typically done through scheduling software like Primavera P6, Microsoft Project, etc.
Question-3: How many baselines are allowed
in any project and which baseline decides the success or failure of the
project?
Answer: A project must have a minimum
one project baseline & that number can go to unlimited. But if you find a
number of baselines that means the planning team is quite inefficient – Avoid
it! The latest baseline defines the success or failure of any project.
Question-4:
What are the Key Performance Indicators – KPI’s?
Answer:
A KPI is type performance measurement on a particular activity where engaged.
KPI’s are defined by keeping a factor “What matters the most”. A careful study
and analysis are required to define because it differs from organization to
organization like a critical KPI for you may not be of any interest of other
same type organization. It is really a diverse area. Examples Rubber lining,
Concrete Work, Machine Failures in a Specific Duration, Plantation, Number of
hiring/firings, Training, etc. etc.
Question-5:
What you normally need to develop a plan?
Answer:
I need the Contract documents to understand the scope, the schedule drawings to
know about areas, Bill of Quantity-BOQ including cost, scheduling software access. Yes,
I need to meet my project team to know about a little productivity rate if I
don’t know in case of any specific activity.
Question-6:
How do you define a critical path?
Answer: The longest path & the minimum
time required to complete a project. A
combination of activities with the total
float as zero are included all.
Question-7:
How much duration a milestone activity normally has?
Answer:
Well, there are different types of milestones are there like start milestone,
finish milestone, etc. but all have ZERO duration.
Question-8:
What is the difference between Free Float & Total Float?
Answer:
Free Float – the amount of time we
can delay an activity without affecting the early start date of its successor
activity. Total Float – the amount
of time we can delay an activity from its early start date without delaying the
whole project finish.
The
free float may affect the start of any activity but total float may affect the
duration of the overall project.
Question-9:
What is the difference between Change order & Variation order
Request?
Answer:
Technically there is no such difference. Change order or Variation request is a
change in scope from the contract but as per contract. If you are much curious
which term should be used the better refer your contract documents. Personally,
I have heard
the term Variation Order but never seen any
documentation for. Everywhere they write a
Change Order
Request.
Question-10:
How to measure the progress of a project?
Answer:
Normally
there are three ways to measure the progress 1)-Man-hours, 2)-Cost &
3)-Quantity
My
preferred method is through Man-hours as It is more logical but I have to
comply as per contractual obligations as most of the companies prefer through
Cost.
By
the way, sometimes we have to use all three methods on a single project to get
more intensive project updated status.
No comments:
Post a Comment